Some improvements ongoing at this time:
Branch M37:
- 10.01.24 Petition for Improvement
- 11.26.24 Order Accepting Petition and Appointing Engineer (Executed)
- 04.30.25 Preliminary Engineer’s Report (Refer to Renville County’s Website)
- 05.22.25 DNR Advisory Report FINAL signed
- 06.24.25 Preliminary Hearing Order – fully executed
- 11.06.25 Final Engineer’s Report (Refer to Renville County’s Website)
- 12.12.25 Advisory Report – Renville Judicial Ditch 15 Br. M37 Final Engineer’s Report
- 12.16.25 – Bolton and Menk Response to Advisory Report
- 2025 JD 15 M37 Property Owners Reports
- 2025.12 JD 15 M37 Viewers Report
- 12.10.25 JD 15M37 Benefits and Damages Statement
Branch 056:
- 02.07.24 Petition for Improvement
- 05.06.24 Amended Petition for Improvement
- 05.28.24 Preliminary Findings and Order
- 10.01.24 Preliminary Engineer’s Report (Refer to Renville County’s Website)
- 11.04.24 BWSR Advisory Report
- 12.09.24 DNR Preliminary Engineer’s Advisory Report – Final signed
- 06.17.25 Combined Final Engineer’s Report – Signed (Refer to Renville County’s Website)
- 07.10.25 Final DNR Advisory Report v2
- 09.23.25 Findings and Final Order JD 15 BR 56 (Executed)
Lateral V Branch C
- 07.30.24 Petition
- 08.26.24 Petition Update
- 09.24.24 Preliminary Findings and Order (Accepting Petition and Appointing Engineer) Original Signatures
- 06.16.25 Preliminary Engineers Report (Refer to Renville County’s Website)
- 07.15.25 DNR Preliminary Advisory Report – Final
- 08.27.25 Preliminary Hearing Order – fully executed
- 12.09.25 Final Engineer’s Report
- 2025 JD 15 Lat V Property Owners Reports
- 2025.12 JD 15 Lat V Amended Viewers Report
- 12.10.25 JD 15 Lat V Benefits and Damages Statement
Completed improvements:
Branch Q:
- Preliminary Engineer’s Report (Br. Q)
- Benefits and Damages Statement (Br. Q) (posted 1/4/23)
- Redetermination of Benefits for Improvement (Br. Q) (posted 1/4/23)
- Advisory Letter (Br. Q) (posted 1/4/23)
- Final Engineer’s Report (Br. Q) (posted 1/4/23)
- Notice of Final Hearing (Br. Q) (posted 1/5/23)
- Public Contract Acceptance Hearing Notice (Wednesday, February 28th, 1pm)
- Final Construction Report (February 5th, 2024)
Branch S:
- Notice of Final Hearing (Br. S)
- Final Engineer’s Report (Br. S)
- Amendment No. 1 to Final Engineer’s Report (Br. S)
- Viewer’s Report (Br. S)
- Final Construction Report (Br. S) (posted 1/11/23)
- Notice of Final Acceptance Hearing (Br. S) (posted 1/11/23)
Branch P1:
- Notice of Final Hearing (Br. P1)
- Final Engineer’s Report (Br. P1)
- Viewer’s Report (Br. P1)
- Public Contract Acceptance Hearing Notice (Wednesday, February 28th, 2pm)
- Final Acceptance Report (January 12, 2024)
Branch A:
- Notice of Final Hearing (Br. A)
- Final Engineer’s Report (Br. A)
- Amendment No. 1 to Final Engineer’s Report (Br. A)
- Amendment No. 2 to Final Engineer’s Report (Br. A)
- Viewer’s Report (Br. A)
- Final Construction Report (Br. A) (posted 1/11/23)
- Notice of Final Acceptance Hearing (Br. A) (posted 1/12/23)
Branch M20: